Issue title: Constraint Programming for Planning and Scheduling
Subtitle: A CSP approach to Robust Scheduling
Article type: Research Article
Authors: Policella, Nicola | Cesta, Amedeo | Oddi, Angelo | Smith, Stephen F.
Affiliations: ISTC-CNR โ Institute for Cognitive Science and Technology, National Research Council of Italy, Italy. E-mails: {name.surname}@istc.cnr.it | The Robotics Institute, Carnegie Mellon University, USA. E-mail: [email protected]
Abstract: Constraint-based approaches to scheduling have typically formulated the problem as one of finding a consistent assignment of start times for each goal activity. In contrast, we are pursuing an approach that operates with a problem formulation more akin to least-commitment frameworks, where the objective is to post sufficient additional precedence constraints between pairs of activities contending for the same resources to ensure feasibility with respect to time and resource constraints. One noteworthy characteristic of this Precedence Constraint Posting (PCP) approach, is that solutions generated in this way generally encapsulate a set of feasible schedules (i.e., a solution contains the sets of activity start times that remain consistent with posted sequencing constraints). Such solutions can offer advantages when there is temporal uncertainty associated with executing activities. In this paper, we consider the problem of generating temporally flexible schedules that possess good robustness properties. We first introduce the concept of a Partial Order Schedule (๐ซ๐ช๐ฎ), a type of temporally flexible schedule in which each embedded temporal solution is also guaranteed to be resource feasible, as a target class of solutions that exploit flexibility in a robust way. We then present and analyze two PCP-based methods for generating ๐ซ๐ช๐ฎs. The first method uses a pure least commitment approach, where the set of all possible time-feasible schedules is successively winnowed into a smaller resource-feasible set. The second method alternatively utilizes a focused analysis of one possible solution, and first generates a single, resource-feasible, fixed-times schedule. This point solution is then transformed into a ๐ซ๐ช๐ฎ in a second post-processing phase. Somewhat surprisingly, this second method is found to be a quite effective means of generating robust schedules.
Keywords: Scheduling, robustness, constraint programming
Journal: AI Communications, vol. 20, no. 3, pp. 163-180, 2007
IOS Press, Inc.
6751 Tepper Drive
Clifton, VA 20124
USA
Tel: +1 703 830 6300
Fax: +1 703 830 2300
[email protected]
For editorial issues, like the status of your submitted paper or proposals, write to [email protected]
IOS Press
Nieuwe Hemweg 6B
1013 BG Amsterdam
The Netherlands
Tel: +31 20 688 3355
Fax: +31 20 687 0091
[email protected]
For editorial issues, permissions, book requests, submissions and proceedings, contact the Amsterdam office [email protected]
Inspirees International (China Office)
Ciyunsi Beili 207(CapitaLand), Bld 1, 7-901
100025, Beijing
China
Free service line: 400 661 8717
Fax: +86 10 8446 7947
[email protected]
For editorial issues, like the status of your submitted paper or proposals, write to [email protected]
ๅฆๆๆจๅจๅบ็ๆน้ข้่ฆๅธฎๅฉๆๆไปปไฝๅปบ, ไปถ่ณ: [email protected]